Tuesday, July 21, 2009

Sheetrockers

So, we are about a week behind schedule, but that's ok. It's looking like we'll be down here in the studio with the cupcake for about a month before we can move back upstairs. Not bad at all, eh?

Update:
- rough electrical and plumbing are done
- sheetrocking and taping/mudding are done
- the tilers started today on both upstairs bathrooms
- 2 coats of primer throughout the house starts tomorrow

We had one of those late night last minute fix-it situations last evening. We decided last week that we wanted to add extra plywood and padding to the floor upstairs to improve the sound-proofing in addition to putting in new hardwood flooring. This, in turn, messed up a lot of what the plumber had done with the toilet flanges. I have no idea how to spell flange. So, Josh made a late night run to HD Pro for more pipe and an extendo-flange thing. He and Jonathan re-jiggered the 500 pound cast iron tub so that it was a touch lower. Josh extendoed the curb to the shower this morning and finished it about 60 seconds before the tilers arrived this morning. Pretty amazing and such a relief that we didn't have to sheepishly tell the tilers that we weren't ready for them....



Thursday, April 16, 2009

Saying "No" to Blowtorching at 1AM

The sheetrocking is comin' along. The boys have made good progress on the ceiling. We are calling today to see if we can schedule the nailing inspection for Tuesday. My fantasy is to have it taped and sanded by the end of next week.

In order to completely finish the sheetrocking, two pipes need to be capped off and the gas line currently feeding the upstairs dryer needs to be capped off. It currently is also feeding the upstairs stove. I can live without a washer and dryer, but I need a stove. So, my superman, J, finally agreed to call the plumber and have him come out for a few hours this week to take care of these things. He's quite capable of doing these things himself, but challenging because he has been getting home from work at midnight. So, this would mean that he would be downstairs blowtorching past midnight. Me no likey. Our lovely plumber has promised to come out by tomorrow at the latest to take care of it for us. Thank God. It was a big deal for my superman to agree to this. I'm very proud of him.

Saturday, January 24, 2009

Not One, But Two Indoor Geysers

Why travel all the way to Yellowstone Park or Taupo to see a beautiful geyser when you can see one at our house? Thursday night was full of excitement. Josh had to continue rerouting some of the plumbing for the heating guys when we had our first geyser in the garage. This was tackled quickly by releasing the pressure on the hose outside.

We then moved upstairs where we decided to tap into the new plumbing currently under our bed. Blowtorch in hand, Lucy and I stood aside to supervise (as always) while he soldered and cut through more pipes. What we had forgotten, however, that the plumber had tested these lines that we wouldn't be using for while, so there was a little water in them and they were, in fact, pressurized. So, the water suddenly shot up in a huge stream towards the ceiling landing all over the floor and the bed. We both collapsed in hysterics and he instructed me to run downstairs and release another valve. The water came to a quick stop and he finished up the soldering while I mopped up the water and changed the sheets. The very strange linoleum flooring in the bedroom made the cleanup rather easy.

A few hours later, we had cold water again enabling us to flush the toilet. Excellent news! Today, Saturday, we now have hot water again and gas for the stove and dryer. It's funny, but after living without any water for a day preventing the toilet from working made it seem like no big deal when I knew we wouldn't have hot water or gas for a few days more.

In other news:
- We got our estimate from the nice tiler, but he wants what I consider to be a not so nice amount of moolah to do the tiling for a pretty simple 4.5x10 ft bathroom. I am now on a quest now to get additional estimates. Yes, I know, that's always a good idea.
- I made other important discoveries in the land of shower doors and tile which I will share later. I figure the geysers are enough for today.

Monday, January 12, 2009

Project Manager & Hostess


There is nothing more exciting for either Miss Lucy or myself than having multiple workmen here at the same time. Today, there are three trucks in the driveway: 2 electricians and the plumber. Phase 1 of the plumbing should be complete today. The inspector is coming out this afternoon. The electrician started this morning. Yippee!

Our project manager/hostess is forever excited by their activities and continually greets the boys each time they go in and out of the front door. She takes her hostessing duties very seriously and always has her duckie or pink hippo in her mouth. She knows what they are doing every minute of the day. Luckily, all the boys all seem to be dog people and are quite happy to have her greet them each and every time. Here she is in her perch by the front door ready to greet her next visitor.

Thursday, January 8, 2009

Plumbing Party


We have an amazing plumber. His name is Felix and he works so damn hard. He forgets to eat sometimes like Josh. He's almost done with Phase 1 of our plumbing work downstairs after only a week. Phase 2 and 3 will come after we've vacated the upstairs and have moved into the studio. Phase 1 includes poking some holes in the ceiling to the second floor in anticipation of Phase 2. So, right now the master bathroom plumbing is poking through in the office (featured above). We have drain pipes and all sorts of weird little things poking up out of the floor in our bedroom under the bed because we're going to be expanding the kitchen a bit. Super glam.

Thursday, December 25, 2008

A Christmas Miracle and Rotten Eggs


Who in their right mind tries to go to Home Depot at 11:45pm on Christmas Eve? We did. And we were very frustrated by the empty parking lot. I mean, aren't there a lot of people other than ourselves that have urgent Depot needs at that hour? Why did we need to go to the Depot, you may be wondering....Well, our Christmas miracle yesterday was heat. Hoorah! The furnace guys were able to temporarily hook up the furnace to some of the existing vents to pipe in some delicious heat for us until the rest of the work can be done. The only trouble was that the house soon smelled like rotten eggs. This is because the intake for the furnace is temporarily pulling air from the downstairs. Hmm, that still doesn't explain the rotten eggs. Well, my friends, that is because phase 1 of the plumbing that's been done down there involves lines that are open which means that the sewer lines are open. Thus, the furnace is pulling refreshing sewer-laced air up into the upstairs.

So, we quickly turned it off and set off for the Depot late last night in hopes of buying some caps to cover up the open pipes. Alas, we were forced to cover the pipes with duct tape instead which seems to have done the job. Josh is featured above covering the pipes. Now we have clean air upstairs. My body is in a bit of shock with this alarming warmness that follows me everywhere I go in the house. It feels unnatural not to have my four layers of snow gear, hat and long underwear on. It's positively delightful.

Sunday, December 21, 2008

Moving the Water Heater - Again

My honey had to move the water heater again to make room for the new furnaces. We moved it to its' new location with the help of a car jack. Very clever. He is soldering the copper pipes to yet another temporary location here, so it's a bit of a maze of pipes. Man does he love his blow torch. It's one of his favorite toys. He always stops in the tool corral at the Depot and stares at the gigantic blow torches. A boy can dream.